Based on the success of the initial Honda Manufacturing
of Alabama plant, and its ahead-of-schedule completion, Honda
Motor Co., Ltd. selected the HHG (Hanscomb-Harbert-Global Performance)
joint venture to build their second state-of-the-art automotive
manufacturing and assembly plant.
Using an aggressive, fast track schedule, Honda and HHG will
have the new assembly line operational twenty one months
after groundbreaking. The 1.1 million square foot facility
is being built on a 1,350-acre tract of land adjacent to
the Phase I plant recently completed by HHG.
The design incorporates Honda’s flexible manufacturing
system in which robotics, assembly platforms and key machinery
can be interchanged, permitting different vehicle models
to be assembled at the same plant.
In addition to the new plant, HHG will oversee the construction
of administrative and employee service buildings to accommodate
the plant’s additional 1,500 employees, as well as
a new Facilities Building (Central Plant). The team is also
managing
site infrastructure improvements, roadways, parking, and
storage and shipping facilities.
HHG is providing comprehensive project and construction management
services, including full-time, on-site project managers to
oversee all phases of the job. The team began by developing
an overall construction plan, including work breakdown structure,
contract contents and project objectives.
CLIENT
Honda Motor Co., Ltd.
FACILITY TYPE
1.1-million sf vehicle manufacturing and assembly plant
CONSTRUCTED VALUE
$400 million
ARCHITECTS
Giffels Associates Limited
BE&K Engineering |
|